§ 110-43. Requirements for subdivision final approval.  


Latest version.
  • After final inspections of subdivisions, the following items are required by the utilities construction manager's office before any water meters will be installed pursuant to this article:

    (1)

    Letter of certification from the engineer of record, stating all lines or lift stations, etc., have been inspected, tested and installed according to the engineer of record's specifications and as-built drawings. The certification must show calculations and test results according to the most recent AWWA standards.

    (2)

    Original letter from state department of environmental protection stating that these facilities have been approved by it and may be put into use.

    (3)

    Three sets of blue line as-built prints and one set reproducible as-built prints.

(Code 1970, § 26-80.6; Ord. No. 87-09, § 16, 3-24-87)