§ 18-43. Temporary permit for site preparation.  


Latest version.
  • Pending the completion of review of plans and specifications, the central permitting manager, at his discretion and with approval of the building official, may authorize the issuance of a temporary permit for site preparation, excavation and construction below grade for the foundation only. The holder of the temporary permit shall proceed only at his own risk and without assurance that a permit for the remainder of the work will be granted or that corrections will not be required in order to meet the applicable laws, regulations, or codes.