A demolition permit is required for the demolition of any structure. When the structure
has electric, gas, water, sewer, or septic connections on site, an inspection will
be required as part of the demolition permit for septic tank abandonment and to ensure
disconnection and/or capping of all water, sewer, electric, and gas connections. Upon
request from the building official, a written demolition plan shall be submitted for
review. Failure to obtain a demolition permit when required and/or to submit a written
demolition plan when requested are violations of this code.
(Ord. No. 07-20, § 1, 9-11-07)